Key statistics

2,600
2,600 tonnes of steel fabricated (Stage 1)
600
600 tonnes of steel fabricated (Stage 2)
350
350 tonnes rubber-lined spooling

Our brief

Inteforge was awarded the detail drafting, supply and fabrication contract for the B2Gold Fekola project in Mali, Africa.

Fekola Gold (2 Stages)
2022/12/Fekola-Gold.jpg

The solution

The scope of work included structural steel, conveyor systems, rubber lined plate work and pipe spooling, ancillary steelwork, sheeting and idler frames.

Inteforge was selected to complete stage two due to our performance during stage one, where we supplied and manufactured the full project expansion scope.