Key statistics

3,000
3,000 tonnes of steelwork
26
26 shop fabricated tanks
5
5 month accelerated delivery schedule

Our brief

Inteforge was engaged to supply over 3,000 tonnes of fabricated steelwork for the Kathleen Valley Lithium Project. This project is designed to produce approximately 500ktpa of high grade spodumene concentrate for use in lithium batteries.

Kathleen Valley Tantalum Refinery
Detailing-services

The solution

Inteforge’s flexible execution approach is seen as critical in ensuring this fast-paced, schedule-driven project is delivered on time. Our integrated approach ensures opportunities to sequence deliveries to suit construction requirements and increase preassembly rates, targeting a significant reduction in peak resourcing and improvement in on-site productivity.